Taiwan High Speed Rail

Taiwan High Speed Rail (THSR) is the high-speed railway of Taiwan consisting of one line that runs approximately 350 km (217 mi) along the west coast, from the capital Taipei to the southern city of Kaohsiung. With construction and operations managed by a private company, Taiwan High Speed Rail Corporation (THSRC), which also operates the line, the total cost of the project was NT$513.3 billion in 1998. At the time it was built, this was one of the world's largest privately funded rail construction schemes. The system's technology is based primarily on Japan's Shinkansen.

Taiwan High Speed Rail
A THSR 700T train running Taiwan High Speed Rail line
Overview
Native name台灣高鐵
OwnerTaiwan High Speed Rail Corporation
LocaleTaiwan
Transit typeHigh-speed railway
Number of lines1
Number of stations12
Annual ridership81,882,961 (2023)  61.8%
Websitethsrc.com.tw
Operation
Began operationJanuary 5, 2007 (2007-01-05)
Operator(s)Taiwan High Speed Rail Corporation
CharacterElevated, Underground, At-grade
Technical
System length350 km (220 mi)
No. of tracks2
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification25 kV 60 Hz AC from overhead catenary
Top speed300km/h
Route map

km
Xizhi Depot
南港
-3.3
Nangang
0.0
台北
5.9
Taipei
板橋
13.1
Banqiao
Hueilung Tunnel
Linkou Tunnel
桃園
42.3
Taoyuan
Hukou Tunnel
新竹
72.2
Hsinchu
Liujia
Liujia Maintenance Base
苗栗
104.9
Miaoli
Fengfu
Miaoli Tunnel
Xinwuri
台中
165.7
Taichung
 metro 
Wurih Depot
Baguashan Tunnel
彰化
193.9
Changhua
雲林
218.5
Yunlin
Taibao Maintenance Base
嘉義
251.6
Chiayi
台南
313.9
Tainan
Shalun
Shalun line
Yanchao Workshop
Zuoying Depot
左營
345.2
Zuoying
Taiwan High Speed Rail Corporation
Traditional Chinese台灣高速鐵路
Simplified Chinese台湾高速铁路
Taiwan High Speed Rail
Traditional Chinese台灣高鐵
Simplified Chinese台湾高铁

The railway opened for service on 5 January 2007, with trains running at a top speed of 300 km/h (186 mph), currently running from Nangang to Zuoying in as little as 1 hour and 45 minutes, reaching almost 90% of Taiwan's population. Most intermediate stations on the line lie outside the cities served; however, a variety of transfer options, such as free shuttle buses, conventional rail, and metros have been constructed to facilitate transport connections.

Ridership initially fell short of forecasts, but grew from fewer than 40,000 passengers per day in the first few months of operation to over 129,000 passengers per day in June 2013. Daily passenger traffic reached 130,000 in 2014, well below the forecast of 240,000 daily passengers for 2008. The system carried its first 100 million passengers by August 2010 and over 200 million passengers had taken the system by December 2012, followed by 400 million by December 2016.

In the initial years of operation, THSRC accumulated debt due to high depreciation charges and interest, largely due to the financial structure set up for the private company. In 2009, THSRC negotiated with the government to change the method of depreciation from depending on concessions on rights to ridership. At the same time, the government also started to help refinance THSRC's loans to assist the company so it could remain operational and profitable. The government injected NT$30 billion as a financial bailout, boosting the government's stake to about 64% from about 37%. The government also extended the rail concession from 35 years to 70 years and terminated the company's build-operate-transfer business model.

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.