Is it possible to synchronize a work item in a project plan in MS Project that it's Assigned To
field is set to a TFS group? I know this works with AD groups, for instance:
Assigned To: Administrators
-> works for AD groups
Assigned To: [My Team Project]\Contributors
-> does not sync in MS Project