I need to fill in the story point for done sprint , because i was recoded it in excel the our management wants to extract reports from jira

James Z
  • 12,209
  • 10
  • 24
  • 44

1 Answers1

0

What I would do is:

  • Create a sprint in Jira, set the appropriate start date and end date (even if these are in the past)
  • Create Jira stories or tasks for each requirement in your Excel spreadsheet
  • Add a story point estimate to each story/task
  • Add the stories/tasks to the sprint you created
  • Mark the sprint as ended