I have a question for control M schedule change. For exmaple: I have three jobs,in my current plan, A,B and C which run in control M daily in sequence with dependency as A->B->C .
I don't want to run job B on Monday so C would start after A on Monday and A> B >C on other days. Is it possible to achieve this without having to create two plans (one which run on Monday for A>C and A>B >C for other days) ?
Thanks a bunch in advance.
''