0

I am trying to create an alert for a dbms scheduler job if it is running for a duration longer than expected. For example, if a job that usually takes 2 hours to run is now running for more than 2.5 hours, I want to be notified.

What would be the best way to do this? Can I use Oracle Enterprise Manager for this?

Kuwali
  • 233
  • 3
  • 13

1 Answers1

0

I achieved this by setting the parameter max_run_duration in the dbms job. An event will be raised if the job run time exceeds the time mentioned in the property.

Kuwali
  • 233
  • 3