How can extended cost be locked, so that it cannot be keyed over? Currently, a qty and a unit cost calculate, but the extended cost can be changed. View of Changed Cost
Asked
Active
Viewed 32 times
1 Answers
1
Create a graph extension for POOrderEntry (I am assuming this is the PO Order Screen)
Add a cache attached handler as follows:
[PXUIField(DisplayName = "Ext. Cost", Enabled = false)]
[PXMergeAttributes(Method = MergeMethod.Merge)]
protected virtual void _(Events.CacheAttached<POLine.curyExtCost> e)
{
}