I can see in Legacy Visualisation in Cognos have a Gantt chart option. I tried to create but it is not working. I have Planned start date and end date and Actual Start date and end date. How can I create a Gantt chart in IBM Cognos Analytics 11.1 R6.
Asked
Active
Viewed 128 times
0
-
1Have you tried RAVE? This link may help https://www.ironsidegroup.com/2014/05/05/gantt-charts-using-cognos-10-2-1-rave-technology/ – VAI Jason Jul 23 '20 at 19:30
-
Yes, I have data set with Planned Start date Planned end date and Actual Start date and Actual end date. Do you think I can create Gantt for four dates I wanted to get two bar one from the planned start and end date and second one Actual Start and end date? – WonderWoman Jul 27 '20 at 19:32
-
Can you share the JSON you have tried so far? – VAI Jason Jul 28 '20 at 17:09