youtrack's Gantt chart is always dealing with Sat and sun as days off , as shown in the image:

Gantt chart

How to change this days so issues can be processed in it. ??

Ahmed Wagdi
  • 3,913
  • 10
  • 50
  • 116

2 Answers2

2

I found that is it possible by just clicking settings(the gear icon near your profile image) >> Time tracking, then define the workdays from this page, and it will be fixed everywhere in your project.

enter image description here

Ahmed Wagdi
  • 3,913
  • 10
  • 50
  • 116
0

It's currently not possible. There're several related feature requests like https://youtrack.jetbrains.com/issue/JT-38441 and https://youtrack.jetbrains.com/issue/JT-29883.