Trying to make a Master Plan on MS Project.
Some sub-projects were inserted with no issues, but for other sub-projects both the work effort and Duration change. Is there a reason for this? If you see the images below, for instance the overall Work effort decreases from 225 to 182 and duration changes as well.
If I try to change this in the inserted Sub-project, then the calculations are off. For instance if i put work to 3 days (resource at 80%), the duration comes as 4.62 rather than 3.75. Even if i put the resource at 100%, the work and duration still don't match.
Could someone please help me with this?