I am facing an issue with the burndown chart in TFS. Fe. Sprint 1 - we have 9 work days. The sprint finishes and there are 6 tasks left so they have to be moved to the next sprint (sprint 2). We are doing the drag and drop of these tasks to the next sprint (sprint 2), but in this case we have a problem with the burndown chart for Sprint 1. This sprint 1 chart will see this sprint as a fully success, because all left over task were moved to the new sprint.
How to handle this problem so we have a good burndown chart for all sprints, even the provious one?