0

If a job (Job A) is already in the Monitoring Queue waiting on a Resource that is being used by another job (Job B) and a workload policy was created to stop any new instance of Job A from running. Will the workload policy only affect the new instance of Job A or will it also affect the Job that is already in the queue and waiting on Job B's resource?

TylerH
  • 20,799
  • 66
  • 75
  • 101
C-Lo
  • 59
  • 8

1 Answers1

0

Workload policies affect all jobs that match the defined filter in the Active Jobs File regardless of when they were ordered. See the below excerpt from the Control-M Workload Automation User Guide. Control-M Workload Automation User Guide: Workload Policies