I have a program in project 2010 with few tasks.

Each task has its own unique-id (i.e. it is being populated automatically into UniqueID column by the project).

For some reason, some of the tasks got deleted.

  1. I want to use again UniqueID of those deleted tasks. Is it possible?
  2. Is there a way to retrieve tasks that were deleted?

Thanks

Nir
  • 601
  • 7
  • 21

1 Answers1

1

In short, the answer to both questions is no. More information:

  1. You cannot reuse the UniqueID of a task that was deleted as the UniqueID is automatically generated. The only control the user has is to add and delete tasks to skip over UniqueIDs or to build a new schedule and painstakingly add the tasks in the correct order to mimic the UniqueIDs in the original schedule.
  2. Yes, if you have a back-up copy of your schedule before you deleted the tasks. Otherwise, no.