In VS2015, how does one associate an existing task with a checked-in changeset? It should be possible, but I've only experienced several dead ends.
Asked
Active
Viewed 97 times
1 Answers
1
Here is one path to success:
- Open the Task
- Click [Links] (between HISTORY and ATTACHMENTS)
- Click the icon below it with the specific Tool Tip "Link to ..."
- Click the Link Type drop-down and select Changeset
- Type in the Changeset or, if you're in an adventurous mood, use the browse button
- Fill in the comment
- Clicking [OK] should add the Changeset to the list of links
- Click [Save]

Tim
- 113
- 2
- 10