So basically, at my workplace we are going to be changing the regular "states" that are in the agile iterations/sprints in Team Foundation Server 2015. We are going from the states "New, Active, Closed" to "New, Coding, Testing, UAT, Done". The WIT for tasks will be edited to reflect the new workflow, and the process config file will be edited to reflect the new states that we are adding/editing. My question is, are the new states that I've added going to be in the reporting automatically? Or, is/are there other step/steps that have to be done for the new states to be included in reporting?
Just wanted some input from others that have done custom states in their iterations for tasks as well.