3

I've just started using taiga to manage some personal projects and I created my first scrum project, but then I realised that the way I'm approaching this project is more suited to kanban.

How do I change between project types? I can't find a setting that says 'switch project types' anywhere.

AncientSwordRage
  • 7,086
  • 19
  • 90
  • 173

1 Answers1

4

There is no master 'switch'. Taiga seems to hold a view of your project that's agnostic to how you display it (separation of concern!). Enabling either view is done via modules.

Here's a picture:

Modules page of Taiga

Just enable the one you want.

AncientSwordRage
  • 7,086
  • 19
  • 90
  • 173