0

I have got a process apllication which I exported from an env. and want to import it in another env. The hogher env. already has an older version of process application running. I could not find any option in Process center to update the process application. Whenever i try to import it, it says that the application already exist. Could anyone let me know how to do it ?

1201ProgramAlarm
  • 32,384
  • 7
  • 42
  • 56
Sunil
  • 93
  • 1
  • 7

2 Answers2

0

On IBM BPM plateforme each application is defined by the prefix try first to edit the one you already have then import the new one and it will work

E.Sophia
  • 49
  • 1
  • 12
0

Change the snapshot name , the server you want to import to has may already snapshot with the same name