I have installed MS Project server 2013 and integrated with SharePoint 2013 I created project web app site, and created Enterprise projects When I click on my project and select task cost view the baseline cost is grayed out and can not be entered can anyone tell me how can I add baseline cost in project task cost view
Asked
Active
Viewed 359 times