Is there a way to configure MS Project 2013 so that it displays in a resource column (eg, resource initials) of the Gantt Chart view of summary tasks the UNION of all resources assigned to its leaf subtasks.
Say for example that I have a summary task S with 2 subtasks S1 & S2, S2 being itself divided into subsubtasks S21 & S22.
Say also that I have allocated resources R1,R2 to S1, resources R2,R3 to S21 and resource R4 to S22.
With my current configuration, the resource initial column of both S2 and S are left blank.
Instead, I would like the resource column of S2 to display R2, R3, R4 and the resource column of S to display R1, R2, R3, R4.
The idea is to be able to visualize all the resources allocated to a summary tasks even when its decomposition in subtasks is hidden.