I am given a start date that I enter into a cell. Then I do a fill down 100 days. It then sequentially will fill in all the days. There is a setting to exclude weekends which I applied. So now it is the next 100 weekdays. The problem I have is that I need to be able to skip other holidays. For example what if I want to skip 7/4/2014 which was a Friday? I can use VBA if necessary.
Asked
Active
Viewed 672 times
0
-
1Untested, but a Google search reveals this: [Autofill Dates Excluding Certain Weekdays](http://www.mrexcel.com/forum/excel-questions/510472-autofill-dates-excluding-certain-weekdays-3.html). – joeschwa Aug 21 '14 at 14:39
-
1Checkout the `WORKDAY(start_date, days, [holidays])` formula as well. The `[holidays]` variable allows you to refer to a range of cells that include the days (holidays) that you want skipped – Jaycal Aug 21 '14 at 15:20
1 Answers
0
Put the start date in A1, e.g. for this financial year:-
4/1/2014
and the list of dates you want to skip in column B starting in B1, e.g. (as in the question)
7/4/2014
and put the formula using WORKDAY as suggested in A2
=WORKDAY(A1,1,B$1:B$1)
and pull the formula down as required.
As a Brit, I've just realised that 7/4/2014 means Fourth of July if the dates are in MM/DD/YYYY format.