I want to create a rrd file with two data souces incouded. One stores the original value the data, name it 'dc'. The other stores the accumulated result of 'dc', name it 'total'. The expected formula is current(total) = previous(total) + current(dc). For example, If I update the data sequence (2, 3, 5, 4, 9) to the rrd file, I want 'dc' is (2, 3, 5, 4, 9) and 'total' is (2, 5, 15, 19, 28).
I tried to create the rrd file with the command line below. The command fails and says that the PREV are not supported with DS COMPUTE.
rrdtool create test.rrd --start 920804700 --step 300 \
DS:dc:GAUGE:600:0:U \
DS:total:COMPUTE:PREV,dc,ADDNAN \
RRA:AVERAGE:0.5:1:1200 \
RRA:MIN:0.5:12:2400 \
RRA:MAX:0.5:12:2400 \
RRA:AVERAGE:0.5:12:2400
Is there an alternative manner to define the DS 'total' (DS:total:COMPUTE:PREV,dc,ADDNAN) ?