How can we show project overheads in Primavera P6? I have tried by level of efforts but it is not showng.
Asked
Active
Viewed 526 times
2 Answers
0
Add Expenses to include Overhead. Go to activities, Bottom Layout
Hope it will work for you.
0
The trick here is to use a special activity type - not a level of effort, but a "WBS Summary".
- Create a new activity.
- Make it a WBS Summary type.
- If you want to assign overhead costs to the entire project, then place it at the very top of your WBS structure (right under the project title).
- Reschedule the project so that it picks up a calculated duration (the duration of the project)
- Assign an expense to it on the Expenses tab of the activity.