We have subdivided a bigger story into some more sub-tasks. But if we close the sub tasks have no effect on the burndown chart which is demotivating. Any ideas how to resolve that?

Machavity
  • 30,841
  • 27
  • 92
  • 100
  • Provide much more information and some code. How should anybody solve your problem without knowing what you're doing? – Jens Erat Feb 08 '13 at 18:43

1 Answers1

1

How are you tracking work in the burndown chart - by story points or hours logged. To see a decrease you will need to have had an Original Estimate or Estimated Story Points. And then you will have had to log hours or have a workflow that sets the Remaining Estimate to 0 when you close the subtask