I'm a bit new to the power calculations for electricity at a colocation facility. I have 2 HP DL580s that are pretty maxed out and this is what the HP power calculators gave me for each server.
Total System Input Requirement (A) - UPS/PDU Circuit Breaker Selection = 9.2 Total System Peak Inrush Current (A) - UPS/PDU Circuit Breaker Selection = 24
Do I need a >48A circuit or just a single >24A circuit to acomodate both servers? Do Colos normally charge double for an A and B redundant configuration? For example if the quote says a 30 Amp circuit, should I assume that is redundant power or budget for double that?