2
votes
1 answer

How do I schedule a stored procedure to run daily at certain time?

I am trying to schedule a stored procedure in Oracle, it should run daily at a certain time, for example at 11:59 pm BEGIN DBMS_SCHEDULER.CREATE_JOB ( job_name => 'BLANKET_WO', job_type => 'STORED_PROCEDURE', job_action …
Ameya
  • 78
  • 1
  • 11
2
votes
1 answer

Sending notification emails when the scheduled job fails in Oracle

I have 4 scheduled jobs,if any of these job fails we have to send alert email regarding job failure to the concerned recipients.how can we do this in Oracle SQL Developer. Can we do this using DBMS_SCHEDULER? What is NOC Alert?
kushi
  • 27
  • 1
  • 5
2
votes
0 answers

Oracle DBMS_SCHEDULER chain step that's always executed

I have a chain, that consists of about 20 steps. One of the final steps is a shell script, that sends report by e-mail. Is there a way to run this step always - no matter if some of the previous steps failed or not? Writing a rule for that step like…
2
votes
1 answer

How to see error logging done by Oracle's DBMS_PARALLEL_EXECUTE Utility ?

I'm running a procedure in parallel by using oracle's dbms parallel execute utility which chunks the workload ; but I have few chunks failing and I can't see any error logs. Is there a way to find out ?
UserOp
  • 174
  • 7
2
votes
1 answer

Oracle dbms_scheduler - react to change of system date

I've got a dbms_scheduler-Job running in Oracle 10.2.0. When I change the system date back to yesterday, the job will wait for one day to continue its work. The reason for this is that next_run_date does not change. This does not happen regularly,…
Peter Lang
  • 54,264
  • 27
  • 148
  • 161
2
votes
0 answers

Oracle: Event is not delivered to chain event step (DBMS_SCHEDULER.DEFINE_CHAIN_EVENT_STEP)

I set up a Scheduler chain to test chain event step's reaction to events. The events (messages) are not delivered. Oracle Database 12c Enterprise Edition Release 12.1.0.2.0 - 64bit Production PL/SQL Release 12.1.0.2.0 - Production "CORE 12.1.0.2.0…
WolfgangB
  • 21
  • 2
2
votes
1 answer

ORA-31600: invalid input value CHAIN for parameter OBJECT_TYPE

I was trying to exported the complete scheduler chain created on Oracle 11g (including steps, rules, etc), when I got this error : ORA-31600: invalid input value CHAIN for parameter OBJECT_TYPE in function GET_DDL ORA-06512: at "SYS.DBMS_METADATA",…
ttirtawi
  • 45
  • 1
  • 6
2
votes
1 answer

Reshcedule oracle DBMS_SCHEDULER job based on condition

I have a daily scheduled job that runs a procedure that sends sms at a particular time daily. But there is not guarantee that the source table for the sms will be populated by that time , i want to be able to reschedule the job for another hour if…
Oxax
  • 91
  • 8
2
votes
1 answer

Is it possible to delete multiple delete statements using parallel ? The delete statements are separate queries affecting different tables

I have the follwing proceudre which is designed to delete the data from transaction table to the audit tbles after certaibn days. This will run every night as a batch process : create or replace PROCEDURE PR_CONNECT_BATCH_MOVE2HIST( …
Krishnendu
  • 125
  • 3
  • 13
2
votes
1 answer

Creating DBMS_SCHEDULER job for oracle

Trying to create job But can't compile it keeps me given this error. There is a question on oracle forums, it say's that i have to create program to wrap it. Is there any workaround for this? -- Created on 30.09.2014 by ALI.ORHAN declare …
Ali Arda Orhan
  • 764
  • 2
  • 9
  • 24
2
votes
1 answer

why , unable to lock row cache entry error (ORA-27355) in Oracle?

I decided to try scheduling my jobs using oracle scheduler, I Created set of jobs and I try to intercommunicate those jobs using queue and I tried with one or two jobs it is running perfectly , but when i use of bunch of jobs (more than 20 jobs) and…
jeyanthinath
  • 1,651
  • 2
  • 15
  • 22
2
votes
1 answer

Associate a scheduler job with a window

Trying to associate a job with a window. Connection should work using the schedule_name but it does not seem to work. Reproducible example creating the window opens every other minute SQL> begin 2 DBMS_SCHEDULER.CREATE_WINDOW ( 3 …
haki
  • 9,389
  • 15
  • 62
  • 110
2
votes
1 answer

Find the job ID of the currently running job / allow only a single job to update a table

I have a "star" database. One is doing some work; another two have jobs that pull metadata into their reference tables, from the first database. I want to stop anyone from updating, deleting or inserting any records on the reference tables in the…
Ben
  • 51,770
  • 36
  • 127
  • 149
2
votes
1 answer

Run exe from DBMS_SCHEDULER

I am kind of new in DMBS_SCHEDULER and I face some problems. I want to run an .exe So I created a Job: begin sys.dbms_scheduler.create_job(job_name => 'FTREC.EXE_1', job_type => 'EXECUTABLE', …
Nianios
  • 1,391
  • 3
  • 20
  • 45
2
votes
1 answer

Create scheduler job to run once in an year

I want to create a job that would run on 2am on the first Sunday in October for every year, I tried with the below code. But got the error like, Error report: ORA-27419: unable to determine valid execution date from repeat interval ORA-06512: at…
Dba
  • 6,511
  • 1
  • 24
  • 33