I have created another PBI state named Closed, which is for a PBI that has not been completed as per DoD. The process is the PBI is copied [to maintain audit trail] into the backlog for prioritisation, re-estimation/evaluation of remaining work, etc and the not-completed PBI is set as closed. This allows the SM and PO to monitor any committment slippage.
In the process config I have the closed state mapped to In Progress, which keeps the Closed PBI in the main backlog. Is there a way to remove it from the backlog? It seems that only Done PBI's are removed.
Process Template is VS SCRUM 2013.2